Read a work item’s risk
This page is for one work item, usually an epic. Blockline shows its risk in two places: a Blockline group in the Details column, and the Blockline panel. Both read the same answer, so they never disagree.
The Details column
A Blockline group is in the right-hand column of:
- every epic and initiative;
- every work item that has a dependency link;
- every work item that has sub-tasks.
A work item with no links and no sub-tasks, below epic level, can neither wait on anything nor hold anything up. It has no group, but its panel still opens.
Nothing is set up: the group is there once the app is installed. Jira may show it closed until you open it. It is laid out like Jira’s own Details, one row for each fact:
- Risk: the level, always written out.
- Date: the work item’s date, with its source in brackets, such as “(due date)”.
- At risk since: since when the work item has been at this level for you. The row has the level’s name, and only an open epic has it.
- Waiting on and Holding up: the work items it waits on and the ones that wait on it, with the first few keys.
Under the rows, in the colour of its level, is the reason: “At risk: PAYC-3 blocks STOR-4 · … · 6 days after this epic’s date”. The last line is the age of the answer and Recalculate, at the bottom left.

For example, STOR-1 has a due date, and its story STOR-4 waits on PAYC-3. PAYC-3’s due date is 6 days after STOR-1’s. So STOR-1 reads At risk, and the reason says “PAYC-3 blocks STOR-4 · … · 6 days after this epic’s date”. The rule behind it is in How risk is judged.
Open the panel
- Open the work item.
- Under its title, press View app actions, the hexagon.
- Pick Blockline. The panel opens on the work item.
On a site where Jira has not moved the app to that row yet, a button named Blockline is in the same place.
What the panel shows
The first lines. The work item’s own level and the reason for it, such as “PAYC-3 blocks STOR-4 · … · 6 days after this epic’s date”. A work item that waits on nothing says “OK · Waits on nothing”. Under them is one small grey line: its date, since when it has been at its level and what happened that day, and how many work items it waits on and holds up. The “what happened” comes from Jira’s change log (“At risk since …, when PAYC-3’s due date moved past this epic’s date”). When the log cannot say, that part is left out.
A story with no date of its own. It cannot be late itself. When its epic is late because of what the story waits on, the story says so: “No date of its own. Through this story, STOR-1 is At risk: PAYC-3 blocks STOR-4 · … · 6 days after STOR-1’s date”.
A blocker that is on time itself. If it is OK or Watch but makes other work late, the panel leads with what it makes late, at the level it causes: “At risk · Makes 2 work items late: MAPP-1 by 45 days (MAPP-3 waits on it), STOR-1 by 6 days (STOR-4 waits on it)”. Under it, “Its own risk: OK. …” says how the blocker itself is doing, or “Its own risk: OK. Waits on nothing”.
Waiting on. Every work item this one waits on, including what its stories and sub-tasks wait on outside it. Each row has:
- the work item and the child it comes through (“blocks STOR-4”);
- its assignee and its status;
- its date and the risk it brings, with the reason.
Holding up. Every work item that waits on this one, with the risk this work item causes it. The team that blocks sees whom it holds back.

For example, in the picture STOR-1 waits on three work items. PAYC-3 is At risk and DATA-2 is Watch because it has no date. MAPP-4 is OK. The epic takes the worst, At risk.
Two buttons at the bottom
- Show dependency map draws the chain upstream of the work item. See Trace a chain with the map.
- Open in Blockline opens the risk board of the work item’s space in a new tab.