A lead time is one number. Behind it are three waits, and Changeline splits it into them so you can see which one to shorten.
The three stages
- Waiting to start: from a work item’s creation to its first move out of To Do.
- In progress: from there to its first move into Done.
- Waiting for release: from Done to the release that shipped it. Where a deployment is a work item reaching Done, there is no such stage, so there are two.
A stage is never negative. A work item released before it was Done spent no time waiting for the release, and one Done before it started spent none in progress.
Where you see them
- Releases tab: a column each, for each release and for each of its work items. Each stage is the median of the work items in the release, with its share of the row’s time in grey and the largest in bold. A line over the table gives each stage’s median over the period.
- Work item panel: one bar in three parts for one work item. See The work item panel.
- Trends tab: change lead time for each release, stacked by the three stages.
- Downloads: the Excel workbook carries the stages.
How they add up
Each median counts only the work items that have that stage, so the three do not always add up to the lead time. They add up for one work item, with one rule:
- With When work starts (the default), the clock starts at the first move out of To Do. Waiting to start is before the clock, so lead time is In progress plus Waiting for release.
- With When the work item is created, the clock starts at creation, so the three stages split the lead time.
Changeline reads each work item’s status history either way, so the three stages are the same whichever start is set. See Settings.
For example, a work item in Checkout 1.9 Clear errors, released on 10 Nov. It waited 2.9 days to start, was in progress for 1 day and waited 2.7 days for the release. Its Change lead time reads 3.7 days: 1 day plus 2.7 days. The 2.9 days came before the clock started, and the bar shows them in purple. If a Jira admin starts lead time at creation, the same work item reads 6.6 days.
What a stage does not say
A stage is a wait in Jira’s statuses, not an hour of someone’s time. A long In progress means the work item stayed out of Done: a bigger work item takes longer. That is why the Not released yet tab shows time in progress and never calls it slow. See The tabs.
DORA here is the research programme at Google behind change lead time, not the EU’s Digital Operational Resilience Act. DORA is a trademark of Google LLC, and Changeline is not made or endorsed by Google.