% complete

Every row shows two percentages, side by side, each with a progress bar. They answer two questions: how much of the estimated work is done, and how many work items are done.

The two percentages

  • % by estimate: story points done ÷ story points total. When no story points are counted, time is used instead: time spent ÷ (time spent + remaining estimate). Time counts only while a remaining estimate is known. Time logged with no remaining estimate says nothing about what is left, so it reads “—”, not 100%.
  • % by work item count: done work items ÷ all work items, across every level below the parent. An admin can count leaf work items only; see Settings.

A parent with nothing estimated below it shows “—” with no bar, never 100%.

For example, the three spaces APP, LOY and PAY have a Total line of 62 of 126 story points, so % by estimate is 62 ÷ 126 = 49%. Of the 37 work items under the eleven epics, 17 are done, so % by work item count is 17 ÷ 37 = 46%.

Choose what % complete is based on

On the tables, % complete by chooses the basis for every row:

  • Auto: story points where a row has them, otherwise time.
  • Story points.
  • Original estimate.
  • Time: time logged ÷ (time logged + time remaining).
  • One of the number fields an admin added.

The line under the control says what the chosen basis measures. The gadget and the panel always use Auto.

For example, APP-1, Push notification preferences, has 6 of 8 story points done, so Auto reads 75%. It has 1h logged and 2h remaining. Choose Time and the row reads 1h ÷ (1h + 2h) = 33%.

Work a percentage leaves out

A percentage can only weigh work that has its basis. When story points are the basis, work estimated only in hours cannot add to it. A done 3-point story beside a 40-hour story that is not started would read 100%, which hides the 40 hours.

So Sumline names each branch that carries an original or remaining estimate and no story points anywhere in it:

  • on the tables, hover the percentage to see the branches;
  • in the panel, a grey line under the figures reads “Left out of the %”;
  • in the downloads, the row’s Exclusion note names them.

Whichever basis a table shows, its percentage names the work it leaves out the same way. On Time, it names the branches that have story points and no time. Subtasks with hours under a story that has points are covered by the story’s points, so they are not named.

% by work item count and the time columns still include the work a percentage leaves out.