Every report covers one period, and every worklog in it lands on one day. The rules are fixed and stated, so the totals can be checked against Jira.

Rolling periods

The Period list on a report’s scope row holds the rolling periods: Today, Yesterday, This week, Last week, Last 2 weeks, This month, Last month, This quarter, Last quarter, This year, Last year, Last 7 days, Last 30 days and Last 90 days. Last 2 weeks is the two whole weeks before this one, for fortnightly sprints and pay runs. They move with the calendar: a saved “Last month” report always shows the month before the current one.

Fixed periods

Custom range, the last item in the Period list: any start and end date, up to 400 days apart. Pick them on the calendar, or write them as “7 Sep 2026”, “7 September 2026” or “2026-09-07”, then press Enter or Apply. A date that reads two ways, such as 10/09/2026, is refused, never guessed.

The arrows

The ‹ and › arrows beside Period step the period back or forward by its own length: a week for This week or Last week, two weeks for Last 2 weeks, a month for This month or Last month, a quarter, a year, or a day for Today and Yesterday; the last 30 days step by 30 days, and a custom range by its own days. A custom range of whole calendar months, from a 1st to a month’s last day, steps by that many months, so the month before September is all of August. The step is a fixed range, so the dates appear under the scope row; save it and the report keeps those dates. Point at either arrow to see which days it shows. The forward arrow is greyed out while the next range has not started.

The day a worklog counts on

A worklog counts on the day it started, in the report’s time zone. By default that is the time zone of the person viewing (from their Jira profile); a report or the site settings can use each author’s own time zone instead. A Jira admin can also set one time zone for everyone in Logline settings, such as Europe/Riga: a report then shows the same days to everyone who opens it, wherever they are, and its period, today, and the times in the Worklogs view follow that zone too. A report can still pick the viewer’s or each author’s zone for itself. Every report names its time zone in the grey line under its figures, “Counted in Europe/Riga”, and How this is counted spells out the rule in force: “A worklog counts on the day it started, in Europe/Riga.” With one zone for everyone, the Worklogs export names it in its time column, “Time (Europe/Riga)”.

Weeks

Weeks start on Monday unless the site settings or the report say otherwise. A week column is headed “Week of” and its first day. A first or last week the period cuts short is headed “Part week” and the days it holds, such as “9–12 Jul”. Per › Auto splits a week by day, a month by week and a quarter or a year by month; Total stays beside the row’s name, however many columns follow.

Hours

Hours are shown as Jira writes them, hours and minutes, 7h 30m, until a Jira admin picks another of four formats in the settings:

  • hours and minutes: 7h 30m (the default);
  • decimal hours: 7.5h;
  • days, hours and minutes: 1d 2h;
  • decimal days: 8.25d, to two places.

A day is the site’s working-day length (8 hours unless an admin changes it). Excel and CSV downloads always hold decimal hours, to two places (76.75), whatever the format on screen.

Totals are added up in seconds and rounded once, so they match Jira to the minute.