Columns, sort and filter
These controls sit on the line above the timesheet, beside Rows, Then by and Per (see Rows and columns): Columns, Sort, Filter and Expected.
Columns
Columns, at the end of the line, picks the estimate columns that work item rows show, beside the period’s hours. All three are picked for a new report.
- Original estimate, Logged (all time) and Remaining, as Jira shows them.
- A lozenge follows the hours of two of them. After Logged (all time) it is the work ratio: Jira’s time spent over the original estimate, from every date. After Remaining it is where the work ends: the time logged plus the remaining estimate, over the original estimate.
- Both lozenges are green up to the estimate, yellow up to 120% of it and red past that. Point at either header to see what it says.
- The downloads keep the work ratio as a column of its own.
- The columns go on work item rows. Pick one while no level is a work item, and Then by becomes Work item.
- With Remaining picked, a row that holds work items says how many of them are over their estimate, such as 2 over (Gaps and overspend).
For example, ACME-2 Checkout redesign has a 12h estimate and 14h logged, so its work ratio is 117%, a yellow lozenge. It has 2h remaining, so it ends at 16h, 133% of the estimate, a red lozenge.
Budget, cost and margin columns
When the first rows are spaces, epics or the client field and some of them have a budget, five more columns follow Amount: Budget, Spent, Left, % used and At completion (Set a budget). The members of one chosen group also see Cost and Margin there (See cost and margin).
Sort
Sort, with its direction button beside it, orders the rows at every level. There is one choice per column:
- Name: a work item by its summary;
- Key: while a level is a work item;
- Total;
- Billable: with a billable rule;
- Amount: with rates;
- Cost and Margin: for the people who see them;
- % used: with budget columns;
- Original estimate, Logged (all time) and Logged %, Remaining and Remaining %: while their columns are picked.
The two with a percent follow the lozenges: Remaining % puts the work that ends furthest past its estimate first. A row that holds work items goes by its highest, then by how many are over.
Name opens ascending and the others largest first; the direction button flips it. The order is saved with the report. It is not in the gadget, which keeps its rows in order of hours.
Filter
The search box keeps only the worklogs whose comment, work item or author holds the text. The chips beside it narrow further.
- Billable only, with a billable rule, keeps the worklogs on billable work items.
- Space keeps the time logged in one space. It shows when the worklogs come from more than one space.
The timesheet adds up just those, and the line beside them says how many: “12 of 116 worklogs · 23h 30m”. The total at the top stays the whole report’s. The filter is the Worklogs view’s too, so switching views keeps it.
Expected hours
With people as rows, or people under Jira groups, the Expected toggle adds Expected and Against expected after Total. Without people as rows, there is no toggle.
- Expected is the working days of the period before today, times the working-day length in Logline settings, plus what the person has logged today, up to one working day. It is the hours a full timesheet would hold so far. A day that is not over counts neither against anyone at nine in the morning nor for them at five.
- Against expected says how far each person is from it, in words: “40h under” in yellow, or “127h over”.
- Holidays and leave are not known to Logline.
- The totals row adds up Expected and leaves the difference empty.
- The export carries both once per person, the difference as a signed number (Against expected (h)), and its totals row adds up both.
For example, last week was five working days of 8 hours, so Expected is 40h for each person. Mitch Davis logged 40h, so his Against expected is a dash. Cassi Owens logged 32h and reads “8h under”. Kevin Campbell logged 41h and reads “1h over”. The totals row adds up 160h expected for the four people and 147h 30m logged, and leaves the difference empty.

A team’s timesheet in one step
When you limit a report to chosen people or a Jira group and choose Show report, with people as rows, Expected switches on, once, and so do Gaps, the columns turning to days where the period allows. That is a team’s timesheet.
With Everyone, a person who logged nothing in the period is not listed. The report says so while Gaps or Expected is on, with Choose people.